Authorize the City Manager to finalize and execute Change Order Nos. 4, 5, and 6 to Bid No. 2023-057, Utility Relocation for IH-635 at US Highway 80 Interchange, with BRCT, LLC dba Black Rock Construction for additional services required in the total amount of $190,933.46.

Agenda Item Passed Introduced September 19, 2024

What this record is

Held by
BRCT, LLC 4 records across this site
Amount
$191K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

BRCT, LLC also holds

Authorize the City Manager to finalize and execute Change Order No. 1, to Bid No. 2024-126, Mesquite to Crandall Water Line Connector Project, with BR… $470K Mesquite, TX Bid No. 2024-126 - Mesquite to Crandall Water Line Connector. (Authorize the City Manager to finalize and execute a contract with BRCT, LLC, dba Black… $5.14M Mesquite, TX Authorize the City Manager to finalize and execute Change Order Nos. 1, 2 and 3 to Bid No. 2023-057, Utility Relocation for IH-635 at US Highway 80 In… $162K Mesquite, TX
Committee
City Council
Introduced
September 19, 2024
On agenda
October 21, 2024
Passed
October 21, 2024

Where it was heard

City Council Oct 21, 2024 Approved Pass