Discuss, consider and/or take action to authorize the County Judge to sign Change Order #5 with Lee Lewis Construction, Inc. for the Court Residential Treatment Center-Phase IV in the amount of $111824.77 and 38 additional days.
What this record is
- Held by
- Lee Lewis Construction, Inc 26 records across this site
- Amount
- $112K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Lee Lewis Construction, Inc also holds
To approve a decrease to the current awarded contract amount of $13,568,203 by $131,544.25 for a total contract amount of $13,436,658.75 for 050 - Tom… Discuss, consider and/or take action to authorize the County Judge to sign an Agreement for Construction Manager-At-Risk with Lee Lewis Construction, … Discuss, consider and/or take action to authorize the County Judge to sign Amendment Two to the Agreement for Construction Manager-At-Risk with Lee Le… Discuss, consider and/or take action to authorize the County Judge to sign Change Order #1 with Lee Lewis Construction, Inc. to add an additional seve… Discuss, consider and/or take action to authorize the County Judge to sign the First Amendment to the Contract for Construction with Lee Lewis Constru…All 26 records for Lee Lewis Construction, Inc →
- Committee
- Commissioners Court Regular Meeting
- Requested by
- Facility Maintenance
- Introduced
- September 17, 2024
- On agenda
- September 23, 2024
- Passed
- September 23, 2024