Consider and take action on a resolution authorizing a construction contract with ISJ Underground Utilities, LLC for the Jarbo Bayou Force Main Replacement Project (WW1801J) in an amount not to exceed $252,318.50, and authorizing a Work Change Directive budget of $25,230 for a total construction budget not to exceed $277,548.50 (Executive Director of Capital Projects)

Agenda Item Approved Introduced August 12, 2024

What this record is

Held by
ISJ Underground Utilities, LLC 4 records across this site
Amount
$252K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

ISJ Underground Utilities, LLC also holds

Consider and take action on a resolution authorizing Change Order No. 1 with ISJ Underground Utilities, LLC related to the East Main 24-inch Force Mai… $190K League City, TX Consider and take action on a resolution authorizing a construction contract with ISJ Underground Utilities, LLC for the Sanitary Sewer Annual Rehab -… $3.25M League City, TX Consider and take action on a resolution authorizing a construction contract with ISJ Underground Utilities, LLC for the Mary Lane and Tallow Forest S… $566K League City, TX
Committee
Capital Projects
Introduced
August 12, 2024
On agenda
September 24, 2024
Passed
September 24, 2024

Where it was heard

City Council Sep 24, 2024 Approved Pass