Consideration to ratify the authorization of the City Manager to enter into an agreement between the City of Laredo and the US Army Corps of Engineers (USACE) in the amount of $6,666,666.67 for the interconnection of the El Pico and Jefferson Water Treatment Plants. Federal funding will pay for the additional $20,000,000.00 needed for the project completion. This agreement allows the City to transfer water from Jefferson Water Treatment Plant to El Pico Water Treatment Plant and vice-versa during a critical emergency situation. Funding is available in the Waterworks Fund- 2024 Water Revenue Bond.

Consent Agenda Passed Introduced March 13, 2026
Committee
City Council
Requested by
Utilities
Introduced
March 13, 2026
On agenda
April 7, 2026
Passed
April 7, 2026

Where it was heard

City Council Apr 7, 2026 approve Pass