26-55
Authorizing the City Manager to approve Change Order No. 1 for Additional Work not included in the original contract and unforeseen and uncontrol underground piping at the Jefferson West High Service Pumps project in the amount of $491,704.82 for RAVA Construction, LLC, Inc. The total contract amount with Change No. 1 is $12,141,704.82 and 689 working days. Funding is available in the Waterworks Fund - 2020 Water Revenue Bond