26-435
Authorizing City Manager for final project acceptance of the construction of the City of Laredo 24-Inch WTR PRV Station inside Airport, including all warranty certificates, release of retainage, and final payment in the amount of $24,290.91 to Southern Trenchless Solutions. The final construction contract amount of $242,909.10 and final contract time of 62 working days. Funding is available in the Water System Fund-2022 Water Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- February 19, 2026
- On agenda
- March 16, 2026