Consideration for approval of FY24-ENG-25 George Pappas Tennis Courts Overlay Rebid Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $36,940.10 to Hellas Construction Inc., Cedar Park, Texas and approval of change order no. 1 in a decrease of $7,178.93. The final construction contract amount is $738,802.07. Funding is available in the 2022 Certificate of Obligation Bond.