Consideration for approval of the construction of the City of Laredo Cuartos Vientos Lomas del Sur Utility Extension & Lift Station, including all warranty certificates, release of retainage, and final payment in the amount of $152,729.70 to Southern Trenchless Solutions. The final construction contract amount of $3,054,594.01 and final contract time of 515 working days. Funding is available in the Sewer System Fund-2022 Sewer Revenue Bond.

Consent Agenda Agenda Ready Introduced January 22, 2026
Committee
City Council
Requested by
Utilities
Introduced
January 22, 2026
On agenda
February 17, 2026

Where it was heard

City Council Feb 17, 2026