Consideration for approval of final payment for the construction of the 24-inch Water Transmission Main from Loop 20 Airport to Bustamante project, including all warranty certificates, release of retainage, and final payment in the amount of $336,940.08 to Southern Trenchless Solutions. The final construction contract amount of $6,738,801.50 and final contract time of 444 working days. Funding is available in the Waterworks Fund - 2020A Water Revenue Bond.