26-1323
Consideration for approval of FY25-ENG-65 High Density Mineral Bond-Street Maintenance Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $107,910.54 to Andale Construction, Inc., Wichita, Kansas and approval of change order no. 1, a decrease of $977,637.24.00. The final construction contract amount is $2,158,210.76. Funding is available in the 2025 Tax Note Fund.
- Committee
- City Council
- Requested by
- Engineering
- Introduced
- June 27, 2026
- On agenda
- August 3, 2026
Where it was heard
City Council City CouncilWatch Laredo
Say what matters to you — a street, a company, a subject — and we will email you when Laredo files something about it.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.