docketcity.com
26-1320

Consideration for approval of FY24-ENG-48 Springfield Avenue Extension Phase 2A Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $144,434.75 to Mage 4Group, Ltd., Laredo, Texas and approval of change order no. 1, a decrease of $382,101.00. The final construction contract amount is $1,478,420.00. Funding is available in the Capital Grants Fund.

Consent Agenda Agenda Ready Introduced June 27, 2026

What this record is

Held by
Mage 4Group, Ltd
Amount
$144K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
City Council
Requested by
Engineering
Introduced
June 27, 2026
On agenda
July 27, 2026

Where it was heard

City Council Jul 27, 2026