Consideration for approval of FY24-ENG-50 North Central Park Inclusive Playground Phase II Project as complete, including all warranty certificates, release of retainage, and final payment in the amount of $61,264.08 to Zertuche Construction Texas, LLC, Laredo, Texas and approval of change order no. 1, an increase of $44,948.56. The final construction contract amount is $1,225,281.56. Funding is available in the Parkland Improvements Fund and Capital Improvements Fund.

Consent Agenda Agenda Ready Introduced June 27, 2026

What this record is

Held by
Zertuche Construction Texas, LLC 6 records across this site
Amount
$61K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Zertuche Construction Texas, LLC also holds

Consideration for approval of Change Order No. 2, an increase of 90 working days to the construction contract with Zertuche Construction Texas, LLC., … Laredo, TX Consideration to award a construction contract to the lowest, responsible, responsive bidder Zertuche Construction Texas LLC, Laredo, Texas in the amo… $1.72M Laredo, TX Consideration for approval of FY25-ENG-16 Fire Station No. 14 Masonry Wall Repairs Project as complete, including all warranty certificates, release o… $5K Laredo, TX Consideration for approval of FY24-ENG-40 Lafayette Tiny Homes Project as complete, including all warranty certificates, release of retainage and fina… $73K Laredo, TX Consideration to award a construction contract to the sole, responsible, responsive bidder Zertuche Construction Texas, LLC., Laredo, Texas, in the am… $1.47M Laredo, TX
Committee
City Council
Requested by
Engineering
Introduced
June 27, 2026
On agenda
July 27, 2026

Where it was heard

City Council Jul 27, 2026