Consideration for approval of Eastern Chacon Creek Interceptor & Drainage Improvements as complete, including all warranty certificates, release of retainage, and final payment in the amount of $219,830.48 to Azar Services, LLC, and approval of change order no. 5 for an amount of $64,602.46. The final construction contract amount is $4,194,227.65 and final contract time is 912 working days. Funding is available in the Environmental Services Fund and Sewer System Funds.
What this record is
- Held by
- Azar Services, LLC
- Amount
- $220K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Requested by
- Engineering
- Introduced
- May 13, 2025
- On agenda
- June 2, 2025