Consideration to reject all bids received for FY21-ENG-08 El Metro Transit Facility - Phase 1 Project, and authorization to rebid the project as the bids received were significantly higher than anticipated. There is no financial impact at this time. 1. Cobalt Construction, Laredo, Texas Total Base Bid: $16,226,288.00 (Bid submittal has a typographical error of $18,226,288.00) 2. Summit Building & Design, Laredo, Texas Total Base Bid: $18,189,572.90 3. RAVA Construction, Houston, Texas Total Base Bid: $21,550,000.00 Refer to attached letter of recommendation from Able City, Laredo, Texas.