25-523
Consideration for approval of FY22-ENG-01 City Institutional Network Fiber Extension as complete, including all warranty certificates and release of retainage in the amount of $34,991.00 to Facility Solutions Group, Corpus Christi, Texas and approval of amendment no. 2 which is an increase in the amount of $17,309.00 and an increase in contract time by 236 calendar days due to lead time from AEP to prepare utility poles for new attachments. The final contract amount is $349,910.00. Funding is available in the Community Development Fund and Public Access- PEG Funds.
What this record is
- Amount
- $35K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Technology
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Requested by
- Engineering
- Introduced
- March 19, 2025
- On agenda
- April 7, 2025
- Passed
- April 7, 2025