Consideration for approval of Change Order No. 1, an increase in the amount of $330,631.06 and an increase of 60 working days to the construction contract with Zertuche Construction Texas, LLC., Laredo, Texas, for the FY24-ENG-17 Economic Development & 311 Offices Relocation. Current contract amount with this Change Order No. 1 is $2,171,116.06 and current contract time is 250 working days. Funding is available in the 2024A and 2025 Certificate of Obligations Bond.

Consent Agenda Agenda Ready Introduced November 4, 2025
Committee
City Council
Requested by
Engineering
Introduced
November 4, 2025
On agenda
December 1, 2025

Where it was heard

City Council Dec 1, 2025