25-1778

Authorizing the City Manager to approval of change order No. 1 in the amount of ($25,989.27-Credit), final payment and release retainage in the amount of $8,387.83 for Southern Trenchless Solutions and accepting the project 54-inch Hobas Pipe project as complete. The final contract amount is $661,552.73. Funding is available in the Sewer System Fund-2020A Sewer Revenue Bond.

Consent Agenda Agenda Ready Introduced September 10, 2025
Committee
City Council
Requested by
Utilities
Introduced
September 10, 2025
On agenda
October 6, 2025

Where it was heard

City Council Oct 6, 2025