25-1778
Authorizing the City Manager to approval of change order No. 1 in the amount of ($25,989.27-Credit), final payment and release retainage in the amount of $8,387.83 for Southern Trenchless Solutions and accepting the project 54-inch Hobas Pipe project as complete. The final contract amount is $661,552.73. Funding is available in the Sewer System Fund-2020A Sewer Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- September 10, 2025
- On agenda
- October 6, 2025
Where it was heard
City CouncilWatch Laredo
Say what matters to you — a street, a company, a subject — and we will email you when Laredo files something about it.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.