Authorizing the City Manager to approve change order No. 1 in the amount of $115,491.76 and increase of 200 working days to the contract time. This change order is required to complete the City of Laredo Sports Complex - Lift Station Project, adding material not included in the original contract and delay on easement acquisition. With this change order the contract amount with Southern Trenchless Solutions of La Feria, Texas will increase the contract to a total of $3,054,594.01 and 350 working days. Funds are available in the Sewer System Fund- 2022 Sewer Revenue Bond.