25-1230

Authorizing the City Manager to approve Change Order No. 1, a credit in the amount of ($40,000.00) for eliminating cathodic protection and increase of 67 working days to the contract time due to unforeseen underground and railroad permits from Southern Trenchless Solutions for the 36-inch Water Transmission Main from Jefferson Water Treatment Plant to Zacate Creek. With this change order the contract amount will decrease the contract to a total of $23,440,540.00 and 287 working days. Funding is available in the Waterworks Fund- 2022 Water Revenue Bond.

Consent Agenda Agenda Ready Introduced July 2, 2025
Committee
City Council
Requested by
Utilities
Introduced
July 2, 2025
On agenda
July 21, 2025

Where it was heard

City Council Jul 21, 2025