24-2210
Authorizing the City Manager to approve a change order to American Electricity Power (AEP), for an increase in the amount not to exceed of $2,264,259.80 which includes a contingency allowance of $100,000.00 to relocate three existing aerial transmission lines and power poles for the utility conflict with existing communications line for the future State Highway 84 (Hachar-Reuthinger Road), as per the Utility Adjustment Certification provided to the Texas Department of Transportation. The final contract amount is $5,235,420.00. Funding is available in the Capital Improvement Fund.
What this record is
- Amount
- $5.24M
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Utilities & energy
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- City Council
- Requested by
- Engineering
- Introduced
- November 14, 2024
- On agenda