24-1904
Consideration to award a construction contract to the lowest, responsible, responsive bidder Zertuche Construction LLC, Laredo, TX in the amount not to exceed a total base bid of $1,840,485.00 for FY24-ENG-17 Economic Development & 311 Offices Relocation including a $160,000.00 contingency allowance, and additive alternate of $76,050.00. The construction contract time for the project is 190 working days. Funding is available in the 2023 and the 2024 Certificate of Obligation Bond. 1. Zertuche Construction, LLC Total Base Bid including Contingency Allowance and Additive Alternate: $1,840,485.00 2. G4 Construction Co. (Mage 4Group, Ltd.) Total Base Bid including Contingency Allowance and Additive Alternate: $2,095,549.00 Refer to attached letter of recommendation from Redline Architecture, Laredo, TX
- Committee
- City Council
- Requested by
- Engineering
- Introduced
- September 19, 2024
- On agenda
- December 2, 2024