24-1339
Authorizing City Manager to approve a change order in the amount of $716,865.36, to Southern Trenchless Solutions of Weslaco, Texas for 24-inch HDPE Water Transmission Main from Loop 20 Airport to Bustamante Project. The updated contract amount is $6,490,490.36. Funding is available in the Waterworks Fund- 2020A Water Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- July 3, 2024
- On agenda
- July 22, 2024
- Passed
- July 22, 2024
Where it was heard
City CouncilWatch Laredo