docketcity.com
24-1099

Authorization to ratify final project acceptance, approve Change Order Number One, a decrease in the amount of $75,000.00, and release of retainage and approval of final payment in the amount of $24,657.15 to Spartan Construction for replacing two belt filter presses at the South Laredo Wastewater Treatment Plant. The final contract amount is reduced to $493,143.00. Funding is available in the Sewer System Fund - 2022 Sewer Revenue Bond.

Consent Agenda Passed Introduced May 21, 2024
Committee
City Council
Requested by
Utilities
Introduced
May 21, 2024
On agenda
June 10, 2024
Passed
June 10, 2024

Where it was heard

City Council Jun 10, 2024 approve Pass