24-0991
Authorizing City Manager to approve final change order in the amount of $23,918.83, release of retainage, final payment in the amount of $ 82,618.84, and final project acceptance to J.S. Haren, LLC for Jefferson Water Treatment Plant Chlorine Feed Improvements Project. The updated contract amount is $817,918.83. The total number of working days is 170. Funding is available in the Waterworks Fund- 2022 Water Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- May 2, 2024
- On agenda
- June 10, 2024
- Passed
- June 10, 2024