24-0805
Consideration for approval of FY24-ENG-04 Winfield Parkway Speed Tables - District VI as complete, approval of change order #1 a total increase in contract amount of $17,790.84 release of retainage, and approval of final payment in the amount of $40,820.34 to ALC Construction Co., Inc., Laredo, Texas. The final construction contract amount is $158,085.84. Funding is available in the 2019 and 2022 CO Bond - District VI Priority Fund.
- Committee
- City Council
- Requested by
- Engineering
- Introduced
- April 5, 2024
- On agenda
- April 15, 2024