24-0584
Authorizing City Manager to approve final project acceptance, approve change order # 1, a decrease in the amount of $ 199,040.00, and release of retainage and approval of final payment in the amount of $129,007.41 to Southern Trenchless Solutions, LLC for the 16-inch Waterline Project. The final contract amount is $3,120,434.09. The total working days are 560 Working Days. Funding is available in the 2020 Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- March 1, 2024
- On agenda
- March 18, 2024
- Passed
- March 18, 2024
Where it was heard
City CouncilWatch Laredo
Say what matters to you — a street, a company, a subject — and we will email you when Laredo files something about it.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.