24-0584
Authorizing City Manager to approve final project acceptance, approve change order # 1, a decrease in the amount of $ 199,040.00, and release of retainage and approval of final payment in the amount of $129,007.41 to Southern Trenchless Solutions, LLC for the 16-inch Waterline Project. The final contract amount is $3,120,434.09. The total working days are 560 Working Days. Funding is available in the 2020 Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- March 1, 2024
- On agenda
- March 18, 2024
- Passed
- March 18, 2024