docketcity.com
24-0537

Authorizing the City Manager to approve Change Order No. 4 for the Eastern Chacon Creek Interceptor & Drainage Improvements for AZAR Services, LLC. This change order is required to complete the project deducting and adding work and materials originally specified for the project. This change order in the amount of $30,595.74 will increase the contract amount to $4,129,625.19 and add 330 working days to the original contract for a total of 842 working days. Funding is available in the 2016 Environmental Certificate of Obligation Bond.

Consent Agenda Passed Introduced February 28, 2024
Committee
City Council
Requested by
Environmental
Introduced
February 28, 2024
On agenda
March 18, 2024
Passed
March 18, 2024

Where it was heard

City Council Mar 18, 2024 approve Pass

Watch Laredo

Say what matters to you — a street, a company, a subject — and we will email you when Laredo files something about it.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top