docketcity.com
24-0465

Authorizing the City Manager to approve change order No. 1 a credit in the amount of ($30,327.50) from SAL Construction Management, LLC for the Santa Rita 36-inch Sewer Interceptor and accepting the project as complete. The final contract amount is $808,927.50. Funding is available in the 2020A Sewer Revenue Bond.

Consent Agenda Passed Introduced January 22, 2024
Committee
City Council
Requested by
Utilities
Introduced
January 22, 2024
On agenda
February 20, 2024
Passed
February 20, 2024

Where it was heard

City Council Feb 20, 2024 approve Pass