24-0465
Authorizing the City Manager to approve change order No. 1 a credit in the amount of ($30,327.50) from SAL Construction Management, LLC for the Santa Rita 36-inch Sewer Interceptor and accepting the project as complete. The final contract amount is $808,927.50. Funding is available in the 2020A Sewer Revenue Bond.
- Committee
- City Council
- Requested by
- Utilities
- Introduced
- January 22, 2024
- On agenda
- February 20, 2024
- Passed