24-0263
Consideration to award contract FY24-035 to A-Squared Water Treatment, Laredo, Texas, in an amount up to $174,385.20 for the pump inspection and alignment of four horizontal split case pumps at the El Pico Water Treatment Plant. Hydro Reliability Services submitted a lower bid and was disqualified because their bid listed thirteen unacceptable exceptions to the bid documents and did not submit licenses engineer documentation. The estimated time for completion of this project is 180 working days upon receipt of order. Funding is available in the Waterworks Construction Fund.