26-5455
Request for approval of a change in contract with McCrory - CTI Services Inc., in connection with final construction of Dula Lane and Related Infrastructure Drainage Improvements Project, adding 51 calendar days, with an addition in the amount of $203,458.80, Job No. 24/0144-2, UPIN 22208MF2H701, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 30.57%.
What this record is
- Held by
- CTI Services Inc
- Amount
- $203K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- August 11, 2026
- On agenda
- August 25, 2026