26-2958
Request for approval of change in contract No. 6 with Allgood Construction Co Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 27 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 10.01%).
- Committee
- Commissioners Court
- Requested by
- Flood Control
- Introduced
- April 30, 2026
- On agenda
- May 14, 2026
- Passed
- May 14, 2026
Where it was heard
Commissioners CourtWatch Harris County
Say what matters to you — a street, a company, a subject — and we will email you when Harris County files something about it.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.