26-1344
Request for approval of a change in contract with Millis Equipment, LLC, in connection with Burnett Bayland Park - Design Phase - 2024, adding 7 calendar days, with an addition in the amount of $640,592.00, Job No. 25/0083-1, UPIN 24104MF3HC01, Precinct 4, MWBE Contracted Goal: 19.53%.
What this record is
- Held by
- Millis Equipment, LLC 9 records across this site
- Amount
- $641K
- Runs until
- no end date published in this record
- Type
- contract
Read automatically from the title of the official record. The source document below is authoritative.
Millis Equipment, LLC also holds
Request for approval of a change in contract with Millis Equipment, LLC in connection with construction of Burnett Bayland Park - Design Phase - 2024,… Request for approval of a change in contract with Millis Equipment LLC, in connection with Hufsmith-Kohrville Rd 2, with an addition in the amount of … Request for approval of a change in contract with Millis Equipment, LLC, in connection with Burnett Bayland Park - Design Phase - 2024, adding 25 cale… Transmittal by the Office of the County Engineer of a correction to Job No. 25/0083-1 on a previously approved change in contract with Millis Equipmen… Request for approval of a change in contract with Millis Equipment, LLC, in connection with Hufsmith-Kohrville Road 2, adding 35 calendar days, with a…All 9 records for Millis Equipment, LLC →
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- February 13, 2026
- On agenda
- February 26, 2026
- Passed
- February 26, 2026