Request for approval of a Preliminary Investment Memo for the Thomas Street Facility - Phase 2 project, for an incremental authorization of $5,000,000 for a total authorization of $5,300,000.

Investment Memo Passed Introduced January 12, 2026
Committee
Commissioners Court
Requested by
County Engineer
Introduced
January 12, 2026
On agenda
January 29, 2026
Passed
January 29, 2026

Where it was heard

Commissioners Court Jan 29, 2026 approved Pass