Request for approval of a change in contract with AAA Asphalt Paving, Inc., in connection with Houmont Park Subdivision Drainage Improvements - 2018 Green River Drive, adding 25 calendar days, with an addition in the amount of $14,000.00, Job No. 25/0065-1, Bond Fund, UPIN 21101MF23H01, Precinct 1, MWBE Contracted Goal: 28.83%, MWBE Current Participation: 100%.

Contract - Amendment Passed Introduced December 22, 2025
Committee
Commissioners Court
Requested by
County Engineer
Introduced
December 22, 2025
On agenda
January 8, 2026
Passed
January 8, 2026

Where it was heard

Commissioners Court Jan 8, 2026 approved Pass