26-0126
Request for approval of change in contract No. 5 with Allgood Construction Company, Inc., for the excavation of Inwood Forest Stormwater Detention Basin, adding 93 calendar days (White Oak Bayou Watershed, Bond ID C-59, Project ID E500-21-00-E002, Job No. 22/0384, Precinct 1, MWBE Contracted Goal: 37%, MWBE Current Participation: 47.65%).
- Committee
- Commissioners Court
- Requested by
- Flood Control
- Introduced
- December 19, 2025
- On agenda
- January 8, 2026
- Passed