25-7077

Request for approval of a construction contract award to MB Western Construction Co., for construction of Scott Street at Beltway 8 Improvements project in the amount of $884,064.00 (Precinct 1, MWBE Contracted Goal: 24.03%).

Contract - Award Passed Introduced October 29, 2025

What this record is

Amount
$884K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Commissioners Court
Requested by
Toll Road Authority
Introduced
October 29, 2025
On agenda
November 13, 2025
Passed
November 13, 2025

Where it was heard

Commissioners Court Nov 13, 2025 approved Pass