Request by Housing and Community Development for approval of change order 33 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,891,685.07 to $25,569,613.91 adding 154 calendar days, MWBE Contracted Goal: 35%.

Contract - Amendment Passed Introduced August 20, 2025

What this record is

Held by
Arch-Con Corporation 10 records across this site
Amount
$25.6M
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Arch-Con Corporation also holds

Request by Housing and Community Development for approval of change order 32 for the HAY Center Project and to increase the construction contract with… $24.9M Harris County, TX Request by Housing and Community Development for approval of partial release of retainage in the amount of $500,000.00 to Arch-Con Corporation for 313… $500K Harris County, TX Request for approval of Change In Contract-8 (CIC-8) for the HAY Center Project and to increase the construction contract with Arch-Con Corporation fr… $24.8M Harris County, TX Request for approval of change order 31 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,804,19… $24.8M Harris County, TX Request for approval of change order 29 for the HAY Center Project and to increase the construction contract with Arch-Con Corporation from $24,230,61… $24.3M Harris County, TX

All 10 records for Arch-Con Corporation →

Committee
Commissioners Court
Requested by
Emergency/Supplemental ARPA
Introduced
August 20, 2025
On agenda
August 26, 2025
Passed
August 26, 2025