Request for approval of a change in contract with Precise Services, Inc., in connection with final construction of Northpointe Boulevard Segment 2, adding 30 calendar days, with an addition in the amount of $44,268.88, Job No. 23/0411-1, UPIN 20104MF1BQ01, Precincts 3 and 4, MWBE Contracted Goal: 31%, MWBE Current Participation: 96.95%.

Contract - Amendment Passed Introduced August 18, 2025
Committee
Commissioners Court
Requested by
County Engineer
Introduced
August 18, 2025
On agenda
August 26, 2025
Passed
August 26, 2025

Where it was heard

Commissioners Court Aug 26, 2025 approved Pass