25-4382
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2023-2, adding 132 calendar days, with a deduction in the amount of $410,133.01, Job No. 23/0293-1, UPIN 23103MF2WQ01, Precinct 3, MWBE Contracted Goal: 33%, MWBE Current Participation: 14.17%.
What this record is
- Held by
- Texas Materials Group, Inc 39 records across this site
- Amount
- $410K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Texas Materials Group, Inc also holds
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Barrett Station (Phase 2 Barre… Bid No. 2026-104 - Hillcrest Street Asphalt Repair. (Authorize the City Manager to finalize and execute a contract with Texas Materials Group, Inc., f… Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Texas Materials Group, Inc. for the 2025 Arterial S… ORDINANCE appropriating $6,358,882.88 out of Dedicated Drainage and Street Renewal Capital Fund - Ad Valorem Tax, as an additional appropriation relat… Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2024-1, adding…All 39 records for Texas Materials Group, Inc →
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- July 1, 2025
- On agenda
- August 7, 2025
- Passed
- August 7, 2025