Request for approval of change in contract No. 2 with Lecon, Inc., for the major maintenance of Cypress Creek and Tributaries, Batch 4, adding 111 calendar days and resulting in an addition of $850,000 to the contract amount (Project ID K100-00-00-X110, Bond ID CI-012, Job No. 23/0237, Precinct 3, MWBE Contracted Goal: 21%, MWBE Current Participation: 9.81%).

Contract - Amendment Passed Introduced April 23, 2025
Committee
Commissioners Court
Requested by
Flood Control
Introduced
April 23, 2025
On agenda
May 8, 2025
Passed
May 8, 2025

Where it was heard

Commissioners Court May 8, 2025 approved Pass