Request for approval of a change in contract with Merchants Bonding Company Mutual, in connection with final construction of Gessner Road, adding 22 calendar days, with a deduction in the amount of $71,140.82, Job No. 20/0362-1, UPIN 18104MF0R801, Precinct 1, Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.

Contract - Amendment Passed Introduced April 23, 2025

What this record is

Held by
Merchants Bonding Company
Amount
$71K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Commissioners Court
Requested by
County Engineer
Introduced
April 23, 2025
On agenda
May 8, 2025
Passed
May 8, 2025

Where it was heard

Commissioners Court May 8, 2025 approved Pass