Request for approval of a change in contract with D&W Contractors, Inc., in connection with Wallisville Road - from 965 feet West of Garth Road to 1,400 feet West of North Main Street - 2017, adding 64 calendar days, with an addition in the amount of $153,640.00, Job No. 23/0225-2, UPIN 18102MF0S601, Precinct 3, MWBE Contracted Goal: 29%, MWBE Current Participation: 46.89%.

Contract - Amendment Passed Introduced March 18, 2025

What this record is

Held by
D&W Contractors, Inc 20 records across this site
Amount
$154K
Runs until
no end date published in this record
Type
contract

Read automatically from the title of the official record. The source document below is authoritative.

D&W Contractors, Inc also holds

Request for approval of a change in contract with D & W Contractors, Inc., in connection with Highland Ridge and Highland Estates Subdivision Drainage… Harris County, TX Request for approval of a change in contract with D & W Contractors, Inc., in connection with Highland Ridge and Highland Estates Subdivision Drainage… $53K Harris County, TX Request for approval of a change in contract with D&W Contractors, Inc., in connection with On-Call - Maintenance - Drainage Improvements in the North… Harris County, TX Request for approval of a change in contract with D & W Contractors, Inc., in connection with On-Call - Maintenance - Concrete Replacement/Repair Sout… Harris County, TX Request for approval of a change in contract with D&W Contractors, Inc., in connection with final construction of Wallisville Road - from 965’ West of… $15K Harris County, TX

All 20 records for D&W Contractors, Inc →

Committee
Commissioners Court
Requested by
County Engineer
Introduced
March 18, 2025
On agenda
March 27, 2025
Passed
March 27, 2025

Where it was heard

Commissioners Court Mar 27, 2025 approved Pass