Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Sidewalks and Undercrossing Project - Fry, adding 31 calendar days, with an addition in the amount of $97,696.60, Job No. 23/0117-3, UPIN 20103N302902, Precinct 4, MWBE Contracted Goal: 33%, MWBE Current Participation: 16.87%.

Contract - Amendment Passed Introduced March 18, 2025

What this record is

Held by
DVL Enterprises, LLC 14 records across this site
Amount
$98K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

DVL Enterprises, LLC also holds

Request for approval of a change in contract with DVL Enterprises LLC in connection with Mound Road Extension from Greenhouse Road along Spring Drive … $8K Harris County, TX Request for approval of a change in contract with DVL Enterprises, LLC in connection with Mound Road Extension from Greenhouse Road along Spring Drive… $3K Harris County, TX Request for approval of a change in contract with DVL Enterprises, LLC in connection with Mound Road Extension from Greenhouse Road along Spring Drive… $3K Harris County, TX Request for approval of a change in contract with DVL Enterprises, LLC, in connection with final construction of Intersection Improvement - Fry Road a… $2K Harris County, TX Request for approval of a change in contract with DVL Enterprises LLC, in connection with final construction of Humble Westfield Road from West Hardy … $377K Harris County, TX

All 14 records for DVL Enterprises, LLC →

Committee
Commissioners Court
Requested by
County Engineer
Introduced
March 18, 2025
On agenda
April 10, 2025
Passed
April 10, 2025

Where it was heard

Commissioners Court Apr 10, 2025 approved Pass