25-1681

Request for approval of change in contract No. 4 with Allgood Construction Co Inc. for the Excavation of Inwood Forest Stormwater Detention Basin, adding 54 calendar days (White Oak Bayou Watershed, Bond ID C-59, Project ID E500-21-00-E002, Job No. 22/0384, Precinct 1, MWBE Contracted Goal: 37%, MWBE Current Participation: 41.91%).

Contract - Amendment Passed Introduced March 12, 2025
Committee
Commissioners Court
Requested by
Flood Control
Introduced
March 12, 2025
On agenda
March 27, 2025
Passed
March 27, 2025

Where it was heard

Commissioners Court Mar 27, 2025 approved Pass