25-1287
Request for approval to partially release retainage to Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-2019, in the amount of $1,175,262.87, Job No. 21/0309, UPIN 20101MF1ET01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 30.59%.
What this record is
- Held by
- Brookstone, LP 14 records across this site
- Amount
- $1.18M
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Brookstone, LP also holds
Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-… Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-… Transmittal by the Office of the County Engineer of a substantial completion certificate with Brookstone LP, in connection with the Harris County Prec… Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-… Request for approval of a change in contract with Brookstone, LP., in connection with Precinct One Administration and Service Center-New Construction-…All 14 records for Brookstone, LP →
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- February 17, 2025
- On agenda
- February 27, 2025
- Passed
- February 27, 2025