25-0843

Request for approval of a change in contract with Total Contracting Limited, in connection with final construction of Sidewalk and Park Project Addicks Clodine-Westpark Sidewalk, with a deduction in the amount of $114,207.53, Job No. 23/0235-1, UPIN 20103N302902, Precinct 4, MWBE Contracted Goal: 32%, MWBE Current Participation: 63.68%.

Contract - Amendment Passed Introduced January 24, 2025

What this record is

Amount
$114K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Commissioners Court
Requested by
County Engineer
Introduced
January 24, 2025
On agenda
February 6, 2025
Passed
February 6, 2025