Request for approval of change in contract No. 2 with Allgood Construction Company Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 119 calendar days and resulting in an addition of $3,081,652 to the contract amount (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 17.72%).

Contract - Amendment Passed Introduced January 8, 2025
Committee
Commissioners Court
Requested by
Flood Control
Introduced
January 8, 2025
On agenda
January 23, 2025
Passed
January 23, 2025

Where it was heard

Commissioners Court Jan 23, 2025 approved Pass