24-6756

Request for approval of change in contract No. 1 with Main Lane Industries, Ltd., for the Cloverleaf Area Drainage Improvements, adding 35 calendar days (Greens Bayou and Carpenters Bayou Watersheds, Bond ID Z-02, Project ID N100-00-00-E001, Job No. 23/0118, Precinct 2, MWDBE Contracted Goal: 25%, MWDBE Current Participation: 57.3%).

Contract - Amendment Passed Introduced October 17, 2024
Committee
Commissioners Court
Requested by
Flood Control
Introduced
October 17, 2024
On agenda
October 29, 2024
Passed
October 29, 2024

Where it was heard

Commissioners Court Oct 29, 2024 approved Pass