docketcity.com
24-5171

Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution System - Parkwood Estates Ph 2 Charrin Dr - 2020, with a deduction in the amount of $253,967.01, Job No. 22/0227-3, UPIN 21289MF1Y501, Precinct 2, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 100%.

Contract - Amendment Passed Introduced August 15, 2024

What this record is

Held by
Reliance Construction Services, LP 21 records across this site
Amount
$254K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Reliance Construction Services, LP also holds

Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution Syst… $241K Harris County, TX Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution Syst… $76K Harris County, TX Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainag… $526 Harris County, TX ORDINANCE approving and authorizing contract with RELIANCE CONSTRUCTION SERVICES, L.P. to provide Construction Services for FY2026 Ditch Re-Establishm… $9.00M Houston, TX ORDINANCE appropriating $5,730,000.00 out of Water & Sewer System Consolidated Construction Fund; approving and authorizing contract with RELIANCE CON… Houston, TX

All 21 records for Reliance Construction Services, LP →

Committee
Commissioners Court
Requested by
County Engineer
Introduced
August 15, 2024
On agenda
August 27, 2024
Passed
August 27, 2024

Where it was heard

Commissioners Court Aug 27, 2024 approved Pass