24-3632
Request for approval of a change in contract with Hayden Paving, Inc., in connection with final construction of Roadway - Crenshaw Road from South Shaver to Allen Genoa Road Reconstruction, adding eight calendar days, with an addition in the amount of $296,158.00, Job No. 20/0027-3, UPIN 22102MF2EE01, Precinct 2, MWDBE Contracted Goal: N/A - project was awarded prior to launch of County’s M/WBE Program.
What this record is
- Held by
- Hayden Paving, Inc 9 records across this site
- Amount
- $296K
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Hayden Paving, Inc also holds
Request for approval of a change in contract with Hayden Paving, Inc., in connection with final construction of BS2N Hardy/Aldine - 2024, with a deduc… Request for approval of a change in contract with Hayden Paving, Inc., in connection with BS2N Hardy/Aldine - 2024, with an addition in the amount of … Request by the Office of the County Engineer for approval to award a contract to Hayden Paving, Inc. in the amount of $3,315,496.79 for Construction S… Request for approval of a change in contract with Hayden Paving, Inc., in connection with Asphalt Package 2024 - 2, adding 14 calendar days, with an a… Request for approval of a change in contract with Hayden Paving, Inc, in connection with Asphalt Package 2024 - 3, adding 150 calendar days, with an a…All 9 records for Hayden Paving, Inc →
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- June 11, 2024
- On agenda
- June 25, 2024
- Passed
- June 25, 2024